Hung Shui Kiu / Ha Tsuen New Development Area

Menu
Home
Design Highlights
Key Parameters Design Highlights
Branding Concept
Innovative Construction
Alliance Pledge
Development Blueprint
Development Milestones Implementation Arrangement
Community Liaison
Community Liaison Centre Community Liaison Service Team Events
Compensation & Rehousing
Info Centre
Latest News Library Consultancy Studies
Text Size
Language
繁體简体
Share
Share to EmailShare to FacebookShare to WeiboShare to Twitter
Text Only Version

Development Milestones

2018.10
Approval of the Hung Shui Kiu and Ha Tsuen Outline Zoning Plan
2020.7
Commencement of works of the First Phase development
2024.1
Chief Executive in Council authorised the proposed road and sewerage works under the Second Phase development
2024
First population intake
Commencement of works of the Second Phase development
2030
Start of population intake of Second Phase development in phases
Development Milestones

Works Progress

First Phase DevelopmentYL/2019/02YL/2020/03
Second Phase Development
YL/2021/02YL/2021/05
YL/2023/01YL/2023/02
YL/2023/03YL/2023/04
YL/2023/05

The site formation and infrastructure works under HSK/HT NDA First Phase development (i.e. Advance Works Phases 1 & 2 and Stage 1 Works) commenced in 2020 in phases.

Advance Works Phases 1 & 2 mainly covers:

  1. site clearance and formation (including land decontamination works) for about 3 hectares (ha) of land, together with the provision of associated engineering infrastructure;
  2. construction of local roads including a one-lane two-way carriageway of about 330 metres (m) long with passing bays connecting Tsing Yick Road to Ng Lau Road;
  3. construction of about 340 m long sewer;
  4. construction of about 1 500 m long water mains; and
  5. implementation of environmental mitigation measures for the works mentioned above.

Advance Works Phase 1 was carried out by CEDD term contract under
Contract No. ED/2020/01 for minor works, and was completed in November 2020.

Advance Works Phase 2 was implemented under Contract No. YL/2019/02 and was completed in December 2024

Stage 1 Works mainly covers:

  1. site clearance and formation (including land decontamination works) for about 14 ha of land, together with the provision of associated engineering infrastructure;
  2. construction of a district distributor road of about 500 m long, which will be a dual two-to-three-lane carriageway connecting to the existing interchange underneath the Kong Sham Western Highway, construction of a single two-lane local road of about 350 m long, widening of a section of Fung Kong Tsuen Road to single two-lane carriageway of about 150 m long and associated junction/road improvements;
  3. construction of about 1,700 m-long sewers, about 360 m-long sewage rising mains and a sewage pumping station (including electrical and mechanical works);
  4. construction of about 1,700 m-long drainage pipes and the associated detention pond;
  5. construction of about 2,300 m-long water mains; and
  6. implementation of environmental mitigation measures and the environmental monitoring and audit programme for the works mentioned above.

Consultant:

AECOM Asia Company Limited
-
Agreement Title: Hung Shui Kiu New Development Area Advance Works, Phases 1 & 2 - Design and Construction
-
Agreement No.: CE 39/2016 (CE)

Mott MacDonald Hong Kong Limited
-
Agreement Title: Hung Shui Kiu New Development Area Stage 1 Works - Design and Construction
-
Agreement No.:CE 56/2016 (CE)

Project information:
https://www.cedd.gov.hk/eng/our-projects/major-projects/index-id-91.html

Contract No. YL/2019/02

Hung Shui Kiu / Ha Tsuen New Development Area Advance Works Phase 2
- Site formation and engineering infrastructure

Scope:
  1. site clearance and formation (including land decontamination works) for about 2.6 hectares of land, together with the provision of associated engineering infrastructure;
  2. construction of local roads including a one-lane two-way carriageway of about 330 metres (m) long with passing bays connecting Tsing Yick Road to Ng Lau Road;
  3. construction of about 340 m long sewer;
  4. construction of about 1 500 m long water mains; and
  5. implementation of environmental mitigation measures for the works mentioned above.

Commencement Date:
August 2020
Completion Date:
December 2024
Contract Sum:
$112 million

Contractor:
Adrian Construction Limited

Contract No.:YL/2020/03

Hung Shui Kiu/Ha Tsuen New Development Area Stage 1 Works
- Site Formation and Engineering Infrastructure

Scope:
  1. site clearance and formation (including land decontamination works) for about 14 hectares of land, together with the provision of associated engineering infrastructure;
  2. construction of a district distributor road of about 500 metres long, which will be a dual two- to three-lane carriageway connecting to the existing interchange underneath the Kong Sham Western Highway, construction of a single two-lane local road of about 350m long, widening of a section of Fung Kong Tsuen Road to single two-lane carriageway of about 150m long and associated junction/road improvements;
  3. construction of about 1 700m-long sewers, about 360m-long sewage rising mains and a sewage pumping station (including electrical and mechanical works);
  4. construction of about 1 700m-long drainage pipes and the associated detention pond;
  5. construction of about 2 300m-long water mains; and
  6. implementation of environmental mitigation measures, environmental monitoring and an audit programme for the works mentioned above.
Commencement Date:
April 2021
Completion Date:
2025 (anticipated)
Contract Sum:
$445 million

Contractor:
China Geo-Engineering Corporation

The detailed design of site formation and infrastructure works under Hung Shui Kiu / Ha Tsuen New Development Area (HSK/HT NDA) Second Phase Development (i.e. Advance Works Phases 3 and Stage 2 Works and related studies) commenced in 2020 in phases.

Advance Works Phase 3 mainly covers:

  1. site clearance and formation (including land decontamination works) of about 51 ha of land together with the provision of associated engineering infrastructure, to ready these formed land for subsequent development of public and private housing, community facilities, commercial and industrial premises and other uses, and for construction of the proposed infrastructure works in paragraph(b) below;
  2. engineering infrastructure works including a primary distributor road, district distributor roads, local roads, sewerage (including pumping stations), drainage, water supply, landscaping, electrical and mechanical ("E&M") and associated works; and
  3. environmental mitigation measures and the EM&A programme for the works above.

Stage 2 Works and related studies mainly cover:

  1. site clearance and formation (including land decontamination works) of about 200 ha of land, together with the provision of associated engineering infrastructure, to ready these formed land for subsequent development of public and private housing, community facilities, commercial and industrial premises, the Green Transit Corridor (comprising the Environmentally Friendly Transport Services, footpaths and cycle tracks) and other uses, and for construction of the proposed infrastructure works in paragraph(b) below;
  2. engineering infrastructure works including district distributor roads, local roads, revitalisation of existing channels, sewerage (including pumping stations), drainage (including pumping stations), water supply, landscaping, E&M and associated works;
  3. environmental mitigation measures and the EM&A programme for the works above; and
  4. related studies covering the following areas:
    (i)
    reviewing the overall public and private housing mix with a view to increasing the share of public housing in view of the latest policy direction;
    (ii)
    reviewing infrastructure provisions to support the revised housing mix and examining the possibility of reprovisioning Tin Ying Road around its current location;
    (iii)
    assessing the feasibility of green and smart initiatives including common utility tunnels for the entire New Development Area development; and
    (iv)
    conducting an urban and green design study for the area around the riverside promenade along the revitalised Tin Shui Wai River Channel in the north-eastern extent of Hung Shui Kiu/Ha Tsuen (HSK/HT) New Development Area (NDA).

Consultant:

Ove Arup & Partners Hong Kong Limited
-
Agreement Title: Hung Shui Kiu/Ha Tsuen New Development Area Package A Works for Second Phase Development - Design and Construction
-
Agreement No. CE 1/2020 (CE)

Ove Arup & Partners Hong Kong Limited
-
Agreement Title: Hung Shui Kiu/Ha Tsuen New Development Area Package B Works for Second Phase Development - Design and Construction
-
Agreement No. CE 71/2020 (CE)

Project information:
https://www.cedd.gov.hk/eng/our-projects/major-projects/index-id-90.html

Contract No.:YL/2021/02

Ground Investigation Works for Hung Shui Kiu/Ha Tsuen New Development Area Package A Works for Second Phase Development

Scope:
Ground investigation works including drillholes, trial pits, in-situ testing, laboratory testing, contamination assessment and geophysical survey.
Contract Date:
June 2022
Completion Date:
December 2023
Contract Sum:
$106 million

Contractor:
Fugro Geotechnical Services Limited

Contract No.:YL/2021/05

Ground Investigation Works for Hung Shui Kiu/Ha Tsuen New Development Area Package B Works for Second Phase Development

Scope:
Ground investigation works including drillholes, trial pits, in-situ testing, laboratory testing, contamination assessment, geophysics survey and comprehensive utilities survey.
Contract Date:
October 2022
Completion Date:
February 2024
Contract Sum:
$58 million

Contractor:
Intrafor Hong Kong Limited

Contract No.: YL/2023/01

Hung Shui Kiu/Ha Tsuen New Development Area Second Phase Development
- Contract 1 - Site Formation and Engineering Infrastructure Works

Scope:
  1. site clearance and formation (including land decontamination works) for about 30 hectares of lands, together with provision of associated engineering infrastructure;
  2. construction of local roads connecting to Ping Ha Road, Shek Po Road and Shek Po East Road;
  3. construction of a community liaison centre;
  4. construction of associated works including water mains, drainage and sewerage works, district cooling mains, cycle tracks, footpaths, box culvert, landscaping works, electrical and mechanical works and other ancillary works; and
  5. implementation of environmental mitigation measures (including noise barriers) and environmental monitoring works for the works mentioned above.

Contract Date:
6 June 2024
Completion Date:
2028
Contract Sum:
$560 million

Contractor:
Sang Hing – Kuly Joint Venture

Contract No.: YL/2023/02

Hung Shui Kiu/Ha Tsuen New Development Area Second Phase Development
- Contract 2 - Fresh Water Service Reservoir and Associated Mainlaying Works

Scope:
  1. site clearance and formation for about 8.5 hectares of lands;
  2. construction of Tan Kwai Tsuen East Fresh Water Service Reservoir and associated roadworks, power supply and landscaping works;
  3. laying of about 4.5 km long fresh water mains and about 3.5 km long flushing water mains; and
  4. implementation of environmental mitigation measures and related environmental monitoring and audit programme for the works mentioned above.

Contract Date:
7 June 2024
Completion Date:
2029
Contract Sum:
$1,997 million

Contractor:
CWBKYH JV

Contract No.: YL/2023/03

Hung Shui Kiu/Ha Tsuen New Development Area Second Phase Development
- Contract 3 – Site Formation and Engineering Infrastructure Works

Scope:
  1. site clearance and formation (including land decontamination works) for about 50 hectares of lands, together with provision of associated engineering infrastructure;
  2. construction of district distributor and local roads connecting Hung Shui Kiu/Ha Tsuen New Development Area to Tin Ha Road and Castle Peak Road;
  3. construction of a pedestrian footbridge and associated stairs and lifts;
  4. construction of a vehicular underpass and associated depressed roads;
  5. realignment and revitalisation of some sections of Tin Sam Channel;
  6. construction of a sewage pumping station;
  7. construction of a common utility enclosure;
  8. reprovision of a sitting-out area near Tung Lei Path;
  9. modification of existing MTR Light Rail Transit junctions at Castle Peak Road;
  10. modification of MTR Tuen Ma Line Emergency Access Point 26 in Tuen Mun;
  11. construction of associated works including water mains, drainage and sewerage works, district cooling mains, cycle tracks, footpaths, box culverts, landscaping works, electrical and mechanical works and other ancillary works; and
  12. implementation of environmental mitigation measures (including noise barriers) and environmental monitoring works for the works mentioned above.

Contract Date:
18 October 2024
Completion Date:
2032
Contract Sum:
$3,363 million

Contractor:
Gammon – Richwell Engineering Joint Venture

Contract No.: YL/2023/04

Hung Shui Kiu/Ha Tsuen New Development Area Second Phase Development
- Contract 4 - Site Formation and Engineering Infrastructure Works

Scope:
  1. site clearance and formation (including land decontamination works) for about 43 hectares of lands, together with provision of associated engineering infrastructure;
  2. construction of district distributor and local roads connecting Hung Shui Kiu/Ha Tsuen New Development Area to Tin Ha Road;
  3. construction of pedestrian footbridges;
  4. construction of a cycle track cum pedestrian subway and associated retaining walls;
  5. revitalisation of some sections of Tin Sam Channel;
  6. construction of a sewage pumping station;
  7. construction of associated works including water mains, drainage and sewerage works, district cooling mains, cycle tracks, footpaths, box culverts, landscaping works, electrical and mechanical works and other ancillary works; and
  8. implementation of environmental mitigation measures (including noise barriers) and environmental monitoring works for the works mentioned above.

Contract Date:
27 September 2024
Completion Date:
2030
Contract Sum:
$1,710 million

Contractor:
Build King - Tung Lee Joint Venture

Contract No.: YL/2023/05

Hung Shui Kiu/Ha Tsuen New Development Area Second Phase Development - Contract 5 - Site Formation and Engineering Infrastructure Works

Scope:
  1. site clearance and formation (including land decontamination works) for about 60 hectares of lands, together with provision of associated engineering infrastructure;
  2. construction of primary distributor, district distributor and local roads connecting Hung Shui Kiu/Ha Tsuen New Development Area to Ping Ha Road, Ha Tsuen Road and Castle Peak Road;
  3. construction of vehicular bridges;
  4. construction of pedestrian footbridges and associated stairs and lifts;
  5. construction of cycle track cum pedestrian subways and associated retaining walls and lifts;
  6. construction of a sewage pumping station;
  7. construction of nature terrain hazard mitigation measures;
  8. installation of closed circuit television cameras for traffic surveillance;
  9. construction of associated works including water mains, drainage and sewerage works, district cooling mains, cycle tracks, footpaths, box culverts, junction improvement works, slope works, retaining walls, street furniture, landscaping works, electrical and mechanical works and other ancillary works; and
  10. implementation of environmental mitigation measures (including noise barriers) and environmental monitoring works for the works mentioned above.

Contract Date:
16 May 2025
Completion Date:
2030
Contract Sum:
$3,828 million

Contractor:
Gammon – Richwell Engineering Joint Venture
West Development Office, Civil Engineering and Development Department
9/F, Sha Tin Government Offices, 1 Sheung Wo Che Road, Sha Tin, New Territories
Tel(852) 2158 5680
Fax(852) 2693 2918
E-mailinfo@hskhtnda.hk
Development Bureau - The Government of the Hong Kong Special Administrative Region of the People's Republic of ChinaCivil Engineering and Development Department - The Government of Hong Kong Special Administrative Region
W3C WAI-AA WCAG 2.1
Important NoticesPrivacy Policy StatementSitemap